Locker Solutions for MMU’s New Science and Engineering Building

Background: Having previously supplied custom lockers for the MMU Institute of Sport, Garran was approached by the main contractor, Bowmer & Kirkland, to provide locker solutions for the £65 million project. This project involved replacing the existing John Dalton West building with a new state-of-the-art Science and Engineering building and refurbishing the remaining Dalton building.

Objective: The primary objectives of this project were to:

  • Provide custom locker solutions tailored to the unique requirements of both existing spaces and new public and teaching areas.
  • Ensure the lockers matched the finishes previously supplied to the Institute of Sport.
  • Successfully install lockers across seven floors in two separate buildings within the set timeframe, despite the demanding refurbishment schedule.

Implementation Steps

    Design Collaboration:
  • Garran worked from the initial drawings provided by BDP Architects, transforming the design intent into working production drawings.
  • Achieved successful sign-off on the designs before proceeding with production.
  • Material Procurement and Planning:
  • Procured materials, including EGGER Maize Yellow HPL and EGGER Soft Black MFC, to match the existing finishes at the Institute of Sport.
  • Chose ASSA Abloy ML51 digital combination locks to ensure consistency with the university’s existing locking systems.
  • Planned production to meet the delivery schedule for completion in mid-2023.
  • Custom Solutions:
    We designed a variety of lockers, including public area mixed-size lockers, custom lockers for void areas in acoustic wall paneling, low-level lockers complementing bespoke balustrades, and bespoke acoustic lockers for the Superlab area. The lockers were spread over seven floors in two separate buildings.
    Planning and Coordination:
  • The installation at the Dalton Building was phased over several months to fit the demanding refurbishment schedule, working in a live building.
  • Adapted to on-site conditions discovered during the works, meeting all challenges and completing the project on schedule with full sign-off.
  • Managed Installation:
  • Garran stored lockers for the John Dalton West building for several months due to delays in the build.
  • Safely delivered all lockers, frames, and panels to the site and stored them for use when required.
  • Completed the installation as planned, in line with the main contractor’s schedule, by February 2024.
  • Detailed schedules and strategies were developed to ensure the installation was efficient and unobtrusive.

Results

  • Successfully installed a variety of custom lockers that met the specific needs of different areas within the new Science and Engineering building.
  • Ensured the lockers matched the existing finishes at the Institute of Sport, maintaining a consistent aesthetic across the university.
  • Completed the installation on schedule, despite the challenges of working in a live building and managing delays.

Conclusion

This project highlights Garran’s capability to deliver complex, customized locker solutions within stringent timelines and challenging conditions. The collaboration with Bowmer & Kirkland and meticulous planning ensured the successful completion of the locker installations, providing functional and aesthetically pleasing solutions for MMU’s new state-of-the-art Science and Engineering building. This case study underscores the importance of flexibility, strategic planning, and strong partnerships in delivering successful large-scale projects.

For more information on this project, other projects or any of the products we supply, contact our team on 02920 859 600 or click here